The average hides the problem
Planning sheets usually hold one lead time per lane, and it is an average, which means it is the one number that describes almost no shipment. A lane with a thirty-five day average and a three day spread can be planned against the average. A lane with the same average and an eighteen day spread cannot, because the shipment that matters is the late one, and the average has nothing to say about it.
The buffer a buyer needs is a function of the spread, not the mean. That is why two importers on the same route, with the same volume, can hold very different stock levels and both be right.
Where the variance actually comes from
Most of it happens before the vessel loads. A booking that gets rolled to the next sailing, a cut-off missed by a few hours because a packing list was late, a container that reaches the terminal after the gate closes: each of these converts a planned departure into a two week delay without anything going wrong at sea.
The rest accumulates in transit and at destination: a transshipment that misses its connection, a port with berth congestion, a customs query that needs a document nobody packed, and inland haulage booked at the last minute. Weather is the factor buyers worry about most and can control least, and in practice it is a smaller contributor than booking discipline.
Guangzhou Shenyue Machinery Technology Co., Ltd. quotes a ship date and an arrival window as two separate lines for this reason. A single date conceals which half of the journey it describes, and that is the half a buyer needs to know when they are deciding how much cover to hold.
Measure three dates, not one
The useful dataset is three columns per shipment: the date the supplier promised, the date the goods actually left, and the date they arrived. The gap between the first two is the part the supplier controls. The gap between the second and third is the part the route controls. Mixing them into one lead-time number is what makes the average useless.
Twenty shipments is enough to see a pattern. Record them as they happen rather than reconstructing them from memory at the end of the year, and separate the delays by cause so the fix lands in the right place.
Sizing the buffer without a statistician
A workable rule for most distributors is to hold cover for the realistic worst gap between two shipments, not for the average one, and to apply that cover only to the lines where a stockout actually stops a sale. Fasteners and filters can carry deep cover cheaply. A final drive cannot, and for those the better answer is a second source and an honest delivery promise rather than more stock.
Review the buffer when the route changes, not only when demand changes. A switch of carrier, a new forwarder, or a different origin port resets the variance, and the old buffer is a guess about a lane that no longer exists.
How we quote a window
Guangzhou Shenyue Machinery Technology Co., Ltd. has supplied excavator parts from Guangzhou since 2007, with 3,000+ part types on the shelf that ship without a production wait, and 100,000+ part numbers available to order where the lead time has to be planned rather than assumed. Quotations separate the two, because shelf stock and available-to-order lines fail in different ways.
We are an independent supplier, formally authorized for five brands — Garrett, Mitsubishi Heavy Industries, TONGMYUNG, NIKURA and Marusan — and not an authorized dealer for Kobelco or other machine brands. Those lines are supplied as genuine parts through original channels or as OEM-quality and aftermarket equivalents, and we will say plainly when a requested date is not realistic rather than book it and explain later.
Where the days go
| Source of delay | What reduces it |
|---|---|
| Booking rolled to a later sailing | Book earlier in the month and confirm the space in writing. |
| Missed documentation cut-off | Close the packing list and invoice before the container is stuffed. |
| Terminal gate closed on arrival | Plan trucking against the actual gate hours, not the published ones. |
| Transshipment connection missed | Prefer direct sailings on critical lanes even at a higher rate. |
| Customs query at destination | Send the full document set ahead and check the importer's requirements. |
Frequently asked
How much safety stock does a thirty-five day lane need?
It depends on the spread, not the thirty-five. If shipments land within three days of plan, cover of a week above the cycle is generous. If they land within eighteen days, a week is not a buffer, it is hope. Measure twenty shipments before choosing a number, and ask the supplier for the ship dates rather than the arrival estimates. Guangzhou Shenyue Machinery Technology Co., Ltd. would rather hand over a year of shipment records than a single lead-time figure.
Should the supplier's promised date be treated as a ship date or an arrival date?
Insist on both being stated separately, because they answer different questions. A ship date is what the supplier controls and what you can hold them to. An arrival date is what your customer cares about and what the route controls. A quotation that gives one number for both is telling you it has not thought about the difference.
Does paying for faster freight reduce the variance?
It reduces the transit time and often the variance as well, because express and premium services have fewer handoffs. It does not fix booking discipline, which is where a large share of the delay originates. Fix the front end of the process before paying for speed at the back end.