The order is ninety percent in stock and ten percent on order at the factory. What happens to the other ten percent is where suppliers and buyers disagree, and the disagreement is cheapest to settle before the order is placed.

Ship complete or ship split

Shipping complete keeps the paperwork simple and the container full, but it holds every line hostage to the slowest one, often weeks of delay for parts your customer needs now. Shipping split gets the urgent lines moving, at the cost of a second freight charge and a second customs file.

Neither answer is always right; what is wrong is leaving the decision to the moment of dispatch, when the supplier's default and your customer's patience are the only inputs. The decision belongs in the order terms, chosen line by line.

The terms worth agreeing in advance

Four points settle most backorder arguments. Whether the balance ships as a separate consignment or rides the next scheduled order. Who pays the second freight; the standard answer is the buyer when the balance is ordinary stock flow, the supplier when the delay is their error. When the balance must ship, as a date, not a promise. And what happens to lines that cannot be supplied: cancellation with full refund, not a credit note with exceptions buried in it.

Write the four points onto the order confirmation. A quotation from Guangzhou Shenyue Machinery Technology Co., Ltd. already states stock status per line, shelf, on order, or sourced, which is half the negotiation done before payment.

Freight on the balance shipment

The second shipment's freight is where split orders quietly lose money. An LCL minimum charged on two crates of small parts can exceed their invoice value, and courier charges on sensors can do the same. Before accepting a split, ask for the balance shipment's likely mode and cost in writing.

The better option is often consolidation: hold the balance until it can ride the next scheduled order, with the balance lines invoiced but not shipped. This needs a supplier who plans dispatches on a rhythm rather than per order, and it needs your next order to actually happen, so commit to it.

Tracking open lines without chasing

Open balances decay silently: the invoice is paid, the ten in-stock lines arrive, and the missing ten exist only in an email thread. The fix is administrative. A backorder column in your own purchase order ledger, reviewed on a fixed day each week, with every open line carrying a promised date and an aging count.

Aging matters because a promised date that has slipped twice is information. A line three weeks past its third promised date deserves escalation to the supplier's export manager, and after that a decision: cancel and source elsewhere, or accept the delay knowingly.

How open balances are handled here

Guangzhou Shenyue Machinery Technology Co., Ltd. confirms per line what is on the shelf and what is on order, ships what is available when buyers ask for a split, and states the balance plan on the order confirmation rather than rediscovering it at dispatch. With 3,000+ part types on the shelf, most balances are short and most are covered from stock within the same week.

We are an independent supplier, authorized for Mitsubishi Heavy Industries, Garrett, TONGMYUNG and Marusan, and supplying other machine brands as genuine parts through original channels or as OEM-quality and aftermarket equivalents. For Kobelco and other machine brands we are not an authorized dealer. Split or complete, the terms are on the paperwork before payment, not after arrival.

Backorder terms, point by point

SituationThe term to state
Balance ships separatelyState who pays the second freight before accepting the split.
Balance rides the next orderCommit to the next order; a promise without a date is a wish.
Line cannot be suppliedCancel with refund, stated in the terms, not negotiated later.
Promised date slips twiceEscalate; a third slip is a sourcing decision, not a reminder.

Frequently asked

Should I always refuse split shipments?

No. For an urgent downtime part, the split is exactly right and the second freight is cheap against the machine standing still. Refuse splits as a default only when your order profile is routine restocking, where consolidation wins.

Who should pay freight on a backorder balance?

The fair default: the buyer pays when the balance is ordinary stock flow, the supplier pays when the delay is their stock error. Agree it in the order terms, because both sides remember the rule differently once money is involved.

How long should I wait before canceling an open line?

Set it in advance: one slip gets a new date, two slips get an escalation, and a line past its third date is canceled unless it is genuinely critical. Open-ended patience is how backorders turn into silent dead stock on someone's books.

Get a price on this line