The cash conversion cycle, in parts numbers
Cash in parts distribution is tied up in three places: stock, receivables and payables. The cycle is days of inventory plus days of receivables minus days of payables, and the result is how long your money is out of the business.
Take a distributor with 120 days of stock, 60 days to collect and 30 days of supplier credit. The cycle is 150 days. If monthly cost of goods is 200,000 dollars, the business needs roughly a million dollars of working capital to stand still, before a single extra container is ordered.
That number explains most of the arguments that get blamed on margin. Guangzhou Shenyue Machinery Technology Co., Ltd. sees the same arithmetic from the supply side of the order, which is why shipment staging and payment terms come up in the first conversation rather than the last.
Four sources, and what each actually costs
Supplier credit is the cheapest source when you can get it and the most expensive when you waste it. Thirty days of terms is free money. A 2 percent discount for payment in ten days, forgone, is an annualized cost of roughly 37 percent, which no bank line will match.
A working capital line from a bank is priced at a reference rate plus a margin and is flexible, but it is repayable on demand and it tends to tighten exactly when the market does. Inventory finance, sometimes called floor planning, advances a percentage of stock value, usually 50 to 70 percent, against monthly reporting and a charge over the goods. Factoring or invoice discounting advances 80 to 90 percent of receivables and charges a discount fee that is easy to compare with a bank rate and easy to underestimate once the ancillary fees are added.
Customer deposits are the source most distributors ignore. A prepayment on a special order is cheaper than any of the others, because it is not debt and it does not need a covenant.
The growth trap
Growth consumes cash before it produces it. A larger order needs stock earlier, ships later and collects later still, while the supplier expects payment on the original schedule. A distributor doubling turnover on the same capital base does not double profit; it runs out of cash somewhere in the second year and blames the customers.
The test is simple. For every additional 100,000 dollars of monthly cost of goods on a 150-day cycle, the business needs about 500,000 dollars more working capital before the first payment comes back. Guangzhou Shenyue Machinery Technology Co., Ltd. would rather agree a staged release schedule at the quotation stage than watch a good customer stall halfway through a growth year.
Telling a finance problem from an assortment problem
Not every cash shortage is a funding problem. If stock days are high because a third of the shelf has not moved in a year, borrowing against that inventory makes the position worse: the lender advances a fraction of cost and the interest accrues on goods that are not selling. If receivables days are drifting because three customers are slow, the fix is credit control rather than a larger line.
Diagnose first. Which of the three numbers moved, and why. Borrowing is the answer only when the cycle is normal for the trade and the volume is real.
What can be arranged from the supply side
Several things in the cycle are decided by the supplier, which is why the conversation is worth having. Staged shipments spread the cash outflow against the production schedule instead of concentrating it. A standing order with monthly releases lets a distributor commit to volume without taking the whole quantity into stock at once. A prepayment discount is cheaper for the buyer than most debt and cheaper for the seller than carrying the receivable.
Guangzhou Shenyue Machinery Technology Co., Ltd. holds 3,000+ part types on the shelf and 100,000+ part numbers available to order, which lets a buyer split an order between what ships now and what can be scheduled. We are an independent supplier, formally authorized for five brands: Garrett, Mitsubishi Heavy Industries, TONGMYUNG, NIKURA and Marusan, and not an authorized dealer for Kobelco or any other machine brand.
Sources of stock finance
| Source | Typical cost and catch |
|---|---|
| Supplier terms | Cheapest when used properly. Forgoing a 2/10 discount costs about 37 percent annualized. |
| Bank working capital line | Reference rate plus margin. Repayable on demand, and tightens with the market. |
| Inventory finance | Advances 50-70 percent of stock. Monthly reporting and a charge over the goods. |
| Customer prepayment | No interest. Requires the buyer to trust the delivery date. |
Frequently asked
How much working capital does a parts distributor need?
Roughly the daily cost of goods multiplied by the cash cycle in days, plus a buffer. A distributor moving 200,000 dollars of cost of goods a month on a 150-day cycle needs about a million dollars, and that figure is a floor rather than a target.
Is inventory finance cheaper than factoring?
Usually the headline rate is lower, but the advance rate is also lower and the reporting burden is heavier. Inventory finance suits slow-moving, high-value stock that a lender can identify and control. Factoring suits a business whose constraint is receivables days rather than stock depth.
Should I take the early payment discount or keep the cash?
Take the discount if you can fund it at anything below roughly 37 percent annualized, which is almost always. Forgoing a 2/10 net 30 discount is one of the most expensive forms of borrowing available, and it is usually invisible because nothing on the statement looks like interest.
Send the machine model, serial number, the part numbers you have and the quantity. That is all we need to quote and confirm fitment before payment.